On November 2, 2026, Finland's Wärtsilä published a comparative analysis claiming that on-site power plants for data centers waiting for grid connection could cut water consumption by 99.97%. The analysis compares medium-speed engines with combined-cycle gas turbines (CCGT), which generate additional power from the turbines' exhaust heat. It is a model-based analysis by a power equipment manufacturer. The steep reduction applies only to water consumed by power generation equipment and does not include server cooling water. Even when meeting the same power demand, the cooling method and the backup capacity held in reserve for equipment outages change not only water consumption but also capital expenditure and required site area.
Breaking down the 99.97% water reduction
To meet 55 GW of data center power demand worldwide, Wärtsilä estimates that power plants using medium-speed engines would consume less than 100,000 m³ of water per year. The CCGT comparison case would consume about 314 million m³ per year. That gap is the basis for the 99.97% figure. The analysis covers on-site generation installed at or near data centers to supply power continuously.
The large difference stems from how the plants are cooled. A CCGT plant generates power with a gas turbine, then uses the exhaust heat to produce steam and generate more power with a steam turbine. In this comparison model, water is used in the steam cycle, in condensing, and in cooling intake air. Medium-speed engines, by contrast, mainly use closed-loop cooling that recirculates cooling water, which keeps consumption low. Note, however, that CCGT plants can use various cooling methods, and water consumption varies with plant configuration.
The report excludes cooling water for the data centers themselves and other facility water use. The 99.97% figure therefore relates only to power generation equipment; total water consumption at a data center also depends on how the servers are cooled.
The 55 GW figure is the upper bound of Wärtsilä's own 2035 deployment outlook, based on announced construction plans and permitting progress. It is a scenario for comparing generation technologies on a global scale, not a firm demand forecast. The assumption that a single technology would meet all demand is likewise a simplification for comparison; the company expects a mix of technologies in practice. The report extends the company's earlier regional facility models to a global scale and evaluates resource consumption and how generation equipment can be used after grid connection.
Backup capacity drives capital costs
When selecting generation equipment, price per kilowatt of rated output alone does not adequately compare the capital required. A large generator also means a large loss of output when a single unit goes offline. Once scheduled maintenance outages and output losses in high temperatures are considered alongside breakdowns, the reserve capacity needed to reliably meet the same demand differs by generation technology.
Wärtsilä analyzed these differences in three regions: Texas in the US, southern England, and Victoria in Australia. Using the power system analysis software PLEXOS, it evaluated 20 years of operation, building in load fluctuations from AI training and inference as well as temperature effects. Power supply was simulated at 5-minute intervals and battery operation at 1-second intervals, assuming that uninterruptible power supplies (UPS) handle load fluctuations of less than one second. The comparison covers entire power systems including batteries, not individual generators.
In the three regional models, the required backup generation capacity was roughly 20–30% of peak demand for medium-speed engines and roughly 85–95% for CCGT. Both figures are in addition to the capacity needed to meet peak demand. The difference arises because the output that must be replaced when equipment goes offline differs between a few large units and multiple smaller ones. The result reflects differences in overall system capacity requirements, not the thermal efficiency of individual generators.
In a model meeting 400 MW (400,000 kW) of demand in Texas, capital investment in medium-speed engine generation was €450 million lower than for CCGT. Including battery investment, the gap widens to €590 million. The differences in equipment configuration needed to meet the same demand and reliability are reflected in the investment figures.
Site area of power equipment meeting the same 400 MW demand (Texas model)
| Power source | Power equipment site area | Site area per MW of data center demand |
|---|---|---|
| Medium-speed engines | About 72,700 m² | About 182 m²/MW |
| Combined-cycle (CCGT) | About 187,700 m² | About 469 m²/MW |
The per-MW site areas in the table are approximations, calculated by dividing the areas shown in Wärtsilä's regional model by 400 MW and rounding to whole numbers. The comparison covers the site area of generation and storage equipment and excludes the data center buildings. Because these are estimates for meeting the same demand and reliability under Texas conditions, deployment in Japan would require evaluation based on location, equipment configuration, and operating conditions.
Using generation equipment after grid connection: a 20-year economic estimate
The report also sets out a concept for continuing to use on-site generation after grid connection is achieved. Before connection, the equipment serves as the data center's main power source; after connection, it serves as emergency power and for balancing supply and demand on the grid. Depending on grid conditions, it can switch to self-generation to reduce power purchased from the grid and, where market rules allow, supply power externally.
However, not all backup generation is assumed to be used for power sales or balancing. The company excludes from the capacity available for grid balancing the equipment held as maintenance reserve and for handling instantaneous output fluctuations. The design aims to use surplus generation capacity while maintaining the reliability of supply to the data center.
The company presents two estimates of economic benefit, tied to the plant's role before and after grid connection. The figure of €196 billion over 20 years is the difference in power supply costs between scenarios in which 55 GW of demand is met by medium-speed engines versus CCGT. It includes annualized capital expenditure and operation and maintenance costs, as well as fuel costs, start-up costs, and applicable carbon taxes.
The separately presented figure of up to €200 billion over 20 years estimates the economic value of avoiding investment in new balancing resources and similar by using post-connection generation equipment for grid balancing. Because it measures something different from the €196 billion figure, the two cannot simply be added together or treated as savings or power sales revenue at individual facilities.
Whether equipment installed while waiting for grid connection can be used over the long term depends not only on its performance but also on contracts with utilities, electricity market rules, and site conditions. Judging the economics of deployment requires evaluating the pre-connection power supply plan and the post-connection operating approach together.
Joint technical evaluation in Japan; emissions and noise remain challenges
In Japan, Tokyo Gas Engineering Solutions (TGES) announced on September 17, 2026 that it had signed a memorandum of understanding with Wärtsilä on a joint technical evaluation. The plan is to combine gas cogeneration, which produces power and uses waste heat simultaneously, with large-scale batteries and energy management systems, to provide power sources for off-grid and similar data centers at an early stage. The project is still at the joint evaluation stage; there is no operating record at commercial data centers in Japan, and the 99.97% water savings have not been confirmed.
Separately from water reduction, CO₂ emissions and impacts on the surrounding environment must also be assessed. Natural gas-fired generation emits CO₂, and Wärtsilä's low-carbon scenarios assume future grid connection and fuel switching. The company's model assumes an average of 10 years of operation independent of the grid before connection, but the period during which the plant serves as the main power source, and cumulative emissions, will vary with the actual connection timing. Nitrogen oxides (NOx) require exhaust treatment such as selective catalytic reduction, and noise requires measures such as soundproofing and silencers.
The company's regional comparison also did not evaluate small modular reactors (SMRs), long-duration energy storage, or solid oxide fuel cells. The differences in economics and resource consumption presented here mainly reflect a comparison between medium-speed engines and CCGT.
In the joint evaluation with TGES, the questions will include whether Japanese site conditions can meet the required power demand and supply reliability, and what equipment configuration, including emissions and noise measures, would be needed. If operating conditions allow the generation equipment to be used effectively after grid connection, the idea of running data centers on self-generation without waiting for the grid could move toward concrete business plans in Japan as well.