A nine-person research team led by Devon A. Stork of Pioneer Labs has released Mars Seed, a reference design for producing habitat construction materials on Mars from the Martian atmosphere and subsurface ice. With a pre-deployed cargo of 20 tons sent to Mars, the in-situ resin production approach would reach the upper limit of the habitable area available under the approach of shipping resin from Earth in about 1,400 sols (Martian days). The team divided the process, from raw material procurement to habitat construction, into 13 subsystems, and calculated the required mass, power, and processing capacity by drawing on existing research and industrial equipment. The results are summarized in an unreviewed arXiv preprint (DOI: 10.48550/arXiv.2611.13064) published on November 9, 2026.

AD

With the same 20-ton cargo, when does local production overtake shipping materials from Earth?

The two approaches the team compared both mine regolith, the layer of sand and rock covering the Martian surface, and use it in the habitat's outer shell. In the approach of shipping resin from Earth, 6.5 of the 20 tons of landed cargo go to power generation equipment, work robots, and mixing and extrusion equipment for building materials. The remaining 13.5 tons are resin and a preformed airtight liner to hold in the indoor air. In Mars Seed, by contrast, all 20 tons go to equipment, and the resin and liner are produced on Mars.

With the landed cargo weight set at 20 tons in both cases and no additional shipments of resin or parts, the habitable area of the Earth-supplied approach is capped at 810 square meters. The team estimates that the in-situ approach reaches this area about 1,400 sols after landing. According to the paper's comparative analysis and Figure 8, after about 1,500 sols (roughly 50 months in Earth time) the area reaches 870 square meters, which is 60 square meters more than the Earth-supplied approach.

This comparison assumes about 1,500 sols between the landing of the pre-deployed cargo and the arrival of a long-stay crew. That corresponds to roughly two synodic periods, the cycle in which Earth and Mars return to nearly the same relative positions. The equipment carried on the pre-deployed flight is to be installed by robots, so how much habitable area can be secured by the time the crew arrives depends on the time needed to install and set up the equipment and on the production period that follows. With the Earth-supplied approach, no further expansion is possible once the materials brought along are used up, whereas the in-situ approach can keep building as long as the equipment keeps running.

Acetic acid production uses half of the 40 kW of generating capacity

Mars Seed assumes installation at mid-latitude sites on Mars where ice exists at shallow depth. Accounting for 6 tons of the equipment is a surface fission reactor with an electrical output of 40 kW. The process that splits atmospheric carbon dioxide into carbon monoxide and oxygen is allotted 6.6 kW, and the process that synthesizes acetic acid from carbon monoxide is allotted 20 kW. Acetic acid serves as a carbon and energy source for microorganisms, but making it alone consumes half of the generating capacity.

Oxygen extracted from the atmosphere is also used for culturing the microorganisms. The combined power consumption of four 1,000 L culture tanks that control temperature and pressure is estimated at 1.6 kW. The water needed for culturing is assumed to be supplied, after the equipment starts up, by 200 L per day newly drawn from subsurface ice plus 1,800 L per day of recycled water. Because supplying raw materials, extracting and purifying the resin, and processing it into building materials are all performed within the same generating capacity, scaling up production requires considering the acetic acid supply and water recycling capacity as well as the culture tanks.

Resin production uses the sPL.001 strain derived from Cupriavidus necator, taking advantage of polyhydroxybutyrate (PHB) that accumulates inside the cells. Output from the four culture tanks was calculated based on a separately conducted 5 L-scale fermentation test and other data. In prior research involving Pioneer Labs, the growth of 16 candidate microorganisms was examined in a simulated Martian medium with an adjusted chemical composition. In a bioRxiv preprint (DOI: 10.64898/2026.09.14.748363), Fatima R. Martin and colleagues report that ground tests using soluble nutrients derived from simulated regolith, acetic acid, and water produced polyhydroxyalkanoate (PHA)-type resin.

There is also an in-situ demonstration of the first step, which uses the Martian atmosphere as a feedstock. MOXIE, the oxygen-generating experiment aboard NASA's Perseverance rover, extracted oxygen from carbon dioxide in the Martian atmosphere 16 times, producing a total of 122 g. NASA disclosed this in its report on the end of the experiment on September 6, 2023, and Mars Seed uses it as a reference for the atmospheric splitting step that precedes acetic acid production.

AD

Microbially produced resin for the habitat's outer shell and airtight liner

The way the produced resin is processed differs by use. The habitat's outer shell uses a composite made by mixing resin-containing microbial cells with regolith. The airtight liner, on the other hand, uses PHB extracted from the cells and processed into an airtight membrane and reinforcing fibers. The design maintains indoor pressure at 57 kPa, and the team estimates that the airtight membrane requires about 440 kg and the reinforcement about 220 kg.

After the outer shell is built, it is covered with roughly 2 meters of regolith for purposes such as radiation protection. The design processes more than 4,000 kg of regolith per day, of which about 3,200 kg goes to the cover and about 800 kg to extracting the inorganic nutrients needed for microbial culture. Because the cover accounts for most of the regolith mined, securing the planned habitable area requires not only resin production but also that mining and hauling operations can continue.

The airtight liner must have not only sufficient strength and durability in the membrane itself but also the ability to stay airtight at the joints with airlocks and valves. It is also necessary to verify whether the outer shell can withstand the load of the cover, and whether the liner can maintain airtightness and strength through long-term changes in internal pressure and temperature. Whether perchlorates derived from regolith might remain in the purified resin also needs investigation.

Can the equipment run autonomously until the crew arrives?

The acetic acid production equipment is designed on the premise that replacement membranes are loaded on the pre-deployed flight. Even if raw materials can be procured on Mars, membrane lifetime and the time needed for replacement would affect the acetic acid supply. After verifying each device individually, the team will need to integrate the whole process, from raw material procurement through culturing, purification, and construction, and confirm that long-term autonomous operation, including parts replacement, is possible. Surveys by candidate site are also essential for the amount of water that can be drawn from subsurface ice and the amount of nutrients that can be extracted from regolith.

The habitable areas presented here are engineering estimates based on a specific cargo weight and equipment configuration. There are no data measuring continuous operation on Mars or resin productivity, and no independent replication integrating comparable equipment has been confirmed. The team estimates that habitable area would reach 2,100 square meters after 10 years in Earth time, but this too is an estimate based on the assumption that the equipment keeps operating.

Going forward, it will be important to run long-term integrated tests of each process on the ground, measure actual resin output including equipment shutdowns and parts replacement, and verify the airtightness and durability of the habitat that is built. These measured values will serve as the basis for assessing the feasibility of devoting the pre-deployed flight's 20 tons to production equipment.