According to a report published by network operator RETN on November 9, 2026, optical network equipment prices are expected to rise roughly 50% in 2026 alone, while lead times have stretched from the traditional three months to 12–15 months, with some orders taking more than 18 months. RETN says telecom operators are now competing with AI data centers for the same semiconductors and optical components. However, public sources do not confirm whether securing components for AI is pushing telecom operators' supply to the back of the line.

AD

Optical Equipment Lead Times Up Four- to Five-Fold

According to RETN, lead times for optical network equipment have grown from three months or less to 12–15 months, an increase of at least four to five times. Taking the traditional lead time as three months, orders that take 18 months or more represent an increase of six times or more. Prices are expected to rise about 50% during 2026, but for telecom operators, the lengthening of lead times is a more serious problem than the price increases.

If procuring equipment takes more than a year, plans to add circuits or upgrade facilities can fall behind. RETN notes that when building new facilities away from existing data center clusters, operators need to coordinate with telecom carriers two to five years before opening.

Note that these lead times come from RETN's report alone, and the specific range of equipment covered has not been disclosed. In its annual report, "The 2026 Annual Resilience Check," the company also reported that in 2025, hardware lead times grew from roughly 8–10 weeks to around 26 weeks in some cases. However, that figure is not limited to optical network equipment, so it should be distinguished from the 12–15 months cited this time.

AI Companies Lock In Optical Component Capacity Ahead of Time

Optical component makers are also struggling to keep supply in line with demand. In July 2026, at the RAISE Summit in Paris, Lumentum's chief executive officer (CEO) said that even as it ramps up production of InP (indium phosphide) lasers, shipments remain more than 30% below customer demand. InP lasers serve as the light source in optical transceivers and are an essential component of optical network equipment.

The CEO explained that while traditional telecom-related customers bought lasers in the hundreds, NVIDIA and the hyperscalers are seeking them in the hundreds of millions. The telecom-related customers referred to here are companies that buy lasers directly, and their position in the supply chain differs from that of telecom operators like RETN. In March 2026, NVIDIA invested $2 billion each in Lumentum and Coherent, and the arrangements are reported to include purchase commitments and access to future production capacity. AI-related companies are stepping up efforts to secure future component supply.

Growth in the optical networking equipment market is also being held back by supply shortages. According to Dell'Oro Group's November 20 announcement, the optical transport equipment market grew 24% year over year in the third quarter of 2026, with sales to major North American cloud operators up 75%. Jimmy Yu, the firm's vice president, said demand far exceeds supply and that, with sufficient supply, growth in the cloud operator segment would have topped 100%. "Supply is determining the size of the market," he said, adding that leading optical equipment makers have already begun taking orders for 2028 deliveries.

Marc Graff, chief financial officer (CFO) of optical equipment leader Ciena, also said in its December 2025 earnings call that supply for the first quarter of fiscal 2026 was "effectively sold out." CEO Gary Smith had expressed hope that lead times would shorten by the end of 2026, but as of November 2026, major manufacturers have begun taking orders for 2028 deliveries.

These statements and market data show that shortages of optical components and the advance securing of production capacity by AI-related companies are both progressing. However, no data comparing lead times for telecom operators and cloud operators under the same conditions has been found. Dell'Oro Group's analysis indicates that sales growth to major cloud operators is also being constrained by supply shortages, so telecom operators are not the only ones facing procurement difficulties.

AD

A Supply Shortage AI Demand Alone Cannot Explain

RETN itself positions AI demand as one factor in the supply shortage. According to the company, shortages of raw materials and skilled labor, energy supply constraints, geopolitical tensions, and logistics problems are also compounding the situation. It adds that telecom operators' postponement of network upgrades to hold down capital expenditure also contributed to longer lead times. The likely explanation is a combination of market-wide supply shortages, telecom operators' capital spending circumstances, and the advance securing of components by AI-related companies.

Component makers are expanding production. Lumentum plans to raise its EML (electro-absorption modulated laser) production capacity by more than 50% from the previous year-end by the end of 2026. However, mass production at its Fab 5, which is being renovated, is scheduled to begin in mid-2028, and some analysts predict the supply-demand imbalance will continue into 2027 and beyond.

Looking ahead, if Lumentum's earnings calls show the shortfall against demand narrowing below 30%, and major manufacturers such as Ciena report shorter lead times, that would support the view that market-wide supply shortages were the main driver of the longer lead times. On the other hand, if lead times of more than 12 months persist even after telecom operators have completed the upgrades they had postponed and component supply has improved, the effects of per-customer supply allocation and AI-related companies' advance securing of supply will also need to be examined.

Because telecom operators and data center operators in Japan source components and equipment from the same global market, they may face similar lead-time extensions. Forecasts that fiber optic cable shortages will last until 2028 have also emerged, and in planning circuit expansions and data center construction, how early equipment and fiber can be secured is becoming critical.