Samsung Electronics plans to raise monthly 9th-generation NAND (V9) capacity at its Xi'an Fab 2 (X2) in China from about 10,000 to about 50,000 300mm wafers, Seoul Economic Daily reported on November 23, 2026. According to the paper, Samsung will install manufacturing equipment in vacant cleanroom space and also convert part of its existing 6th-generation NAND (V6) production lines to V9. The plan would expand V9 monthly capacity roughly fivefold, but the increase combines a boost to the fab's overall capacity with the conversion of lines from an older generation.

AD

The Difference Between 50,000 Wafers of Capacity and a 40,000-Wafer Production Target

Reuters also reported in October 2026 on Samsung's plans to upgrade production lines at its Xi'an plant. However, the 50,000 wafers per month reported by Seoul Economic Daily is V9 capacity at Xi'an Fab 2, whereas the 40,000 wafers per month reported by Reuters is a V9 production target for the Xi'an site as a whole. The two figures measure different things.

Date / Outlet Scope Timing in the plan Metric
Nov. 23, 2026 / Seoul Economic Daily V9 at Xi'an Fab 2 (X2), 300mm wafer equivalent Line conversion to be completed by November 2027 Monthly capacity of about 50,000 wafers
Oct. 21, 2026 / Reuters V9 at the Xi'an site By December 2027 Monthly production target of 40,000 wafers

The plan to switch the Xi'an plant to V9 reported in October also included a short-term production target. According to Reuters, people familiar with the plan said the target for December 2026 was 5,000 wafers per month. Reuters, however, reported these figures as targets for the Xi'an site and did not specify whether they apply only to X2. Both reports rely on anonymous sources; the latest one adds specifics on equipment additions at X2, the conversion of existing lines and the deadline for the retrofit.

Equipment Additions and Conversion of 6th-Gen NAND Lines

According to Seoul Economic Daily, X2 began operating in 2020 and currently produces both V6 and V9. Samsung Electronics reportedly began dispatching mass-production engineers from its Hwaseong and Pyeongtaek sites in South Korea in November 2026. The company plans to build a new electroplating line in vacant cleanroom space, bring in equipment around February 2027 and finish converting the production lines by November of that year.

All of the new capacity secured through the equipment additions will be allocated to V9. Samsung also plans to convert 20–30% of its existing V6 lines to V9, the paper said. While the equipment additions raise X2's overall capacity, converting V6 lines redirects existing capacity to V9. The plan to lift V9 monthly capacity from about 10,000 to about 50,000 wafers includes both.

Germany's ComputerBase cited a post on X by Jukan referring to the Seoul Economic Daily report on November 24, saying that before the retrofit X2 produces 100,000 V6 wafers and 10,000 V9 wafers per month. In the breakdown the outlet presented, new equipment adds 20,000 wafers of monthly capacity, bringing X2's total to 130,000 wafers per month. The 20–30% figure reported by Seoul Economic Daily, meanwhile, is the share of existing V6 lines to be converted to V9; the number of V9 wafers the converted lines can process each month has not been confirmed.

U.S. export controls on chipmaking equipment also bear on the expansion. In an August 2025 announcement, the U.S. Commerce Department's Bureau of Industry and Security (BIS) said it intends to permit exports needed to operate existing fabs in China owned by companies covered by the former Validated End-User (VEU) program. It said it would not permit exports aimed at expanding capacity or upgrading technology. In its October 2026 response to Reuters, Samsung Electronics said it was consulting closely with the U.S. government and upgrading equipment to meet demand from customers in the U.S. and elsewhere. At that time, it said capacity expansion and the construction of new fabs were not part of the plan. Whether individual export licenses have been granted for the X2 equipment, and their scope, has not been confirmed.

AD

NAND Generation Shifts Also Change the Supply of Storage Capacity

When NAND moves to a new generation, the amount of storage obtained from the same number of wafers also changes. According to Seoul Economic Daily, V9 uses a structure with 286 stacked layers of memory cells. In its April 2024 announcement of the start of mass production, Samsung unveiled a 1-terabit triple-level cell (TLC) product that stores 3 bits per memory cell.

The company said that, through smaller memory cells and the elimination of unnecessary channel holes (the vertical holes that run through the stacked memory cells), bit density per unit area improved by about 50% over the 8th generation. At the same time, the more layers are stacked, the harder it becomes to carry out the etching process that forms deep channel holes.

If V6 lines at X2 are converted to V9, calculating the supply in terms of storage capacity requires considering not only the number of wafers processed for each generation but also chip area, storage capacity and manufacturing yield. The improvement in bit density versus the 8th generation alone is not enough to calculate the increase in supply from switching V6 to V9.

SSD Demand for AI Servers and 2027 NAND Prices

Enterprise SSDs using 9th-generation NAND have already entered mass production. The PM1763, whose mass production Samsung Electronics announced in July 2026, is an enterprise SSD for servers handling AI and high-performance computing (HPC). It combines 9th-generation V-NAND with a controller built on a 4nm process and uses a PCIe 6.0 interface. The product announcement, however, does not say where the NAND it uses is manufactured.

In its third-quarter 2026 results, Samsung Electronics said that, with limited supply capacity, it adopted a product mix focused on AI-related products and responded to rising demand for server SSDs. Looking ahead to 2027, it said it expects demand for AI-related memory to far exceed supply.

Meanwhile, TrendForce's November 25 research found that Chinese cloud providers, worried about GPU shortages, scaled back their 2027 enterprise SSD procurement plans in mid-Q4 2026. The reduction in orders from Chinese players is larger than the increase from North American cloud providers, it said. TrendForce also forecasts that in the PC and smartphone markets, manufacturers will cut the NAND capacity they install to hold down component costs.

TrendForce expects NAND bit supply to grow in 2027 as some NAND makers expand capacity and move processes to newer generations. Based on this supply-demand outlook, it forecast that global NAND contract prices will fall overall that year. This covers a different market from the tight AI-related memory supply Samsung described: even if demand for AI products is strong, supply could exceed demand in the NAND market as a whole.

How much the capacity increase at Xi'an Fab 2 will affect the NAND market depends on whether equipment installation and line conversion proceed as scheduled, and how far V9 mass-production volume and yield improve after the retrofit. In assessing 2027 NAND prices, cloud providers' ordering trends will be an important factor, along with the progress of each manufacturer's capacity expansion and generational transition.