On November 26, 2026, JR East announced that it will install film-type perovskite solar cells on the roof of Platform 2 (tracks 3 and 4) at Shinagawa Station. This will be the company's first full-scale adoption at a railway facility, with operations scheduled to begin in the first half of fiscal 2027. The electricity generated will be used for platform lighting and other purposes. At Hakata Station, where power generation experiments on a platform roof have already begun, JGC, the company in charge of installation, completed the work within the limited hours available at night. At Shinagawa Station, JR East will verify not only power generation performance but also ease of installation at an actual railway facility.

AD

48 solar panels expected to generate about 5,800 kWh per year

At Shinagawa Station, 48 film-type perovskite solar cells made by Sekisui Solar Film will be installed over 69 ㎡ of the platform roof. The generating capacity is 5.28 kW, and annual output is expected to be about 5,800 kWh. The electricity is planned for use in platform lighting, lighting in the platform office, power outlets, and similar applications.

JR East has so far been introducing solar power systems at stations and rolling stock depots. However, conventional solar panels have been limited in where they can be installed because of weight and space constraints. Film-type perovskite solar cells are lightweight and flexible, so they may be installable in places where conventional panels were difficult to use. The Shinagawa Station project was selected for the perovskite solar cell equipment introduction support program run jointly by the Ministry of the Environment, the Ministry of Economy, Trade and Industry, and the Ministry of Land, Infrastructure, Transport and Tourism.

Following the Hakata Station experiment, Shinagawa plans to supply power for lighting and more

On October 21, 2025, JGC, JR Kyushu, and Enecoat Technologies began a joint demonstration of film-type perovskite solar cells at Hakata Station. At Hakata, power generation experiments use equipment of around 100 W, whereas Shinagawa will introduce equipment with a capacity of 5.28 kW and plans to supply power to platform lighting and other uses. According to JGC, a 3 kW-class mock-up has also been installed on the Hakata Station roof, separate from the experimental equipment. The Hakata demonstration is checking power generation performance and installation condition, while also collecting data on output and durability.

According to JGC's installation report on the work it carried out at Hakata, the time available for construction was limited to short windows at night. The company therefore adopted a sheet-based method, attaching power generation modules pre-assembled on pipe frames to the folded-plate roof, and completed the work within the allotted time. Even when the solar cells themselves are lightweight, introducing them at railway facilities requires a fixing method suited to the roof structure and a procedure that can be completed within limited working hours.

AD

Verifying performance and installability with an eye to wider adoption at other railway facilities

At Shinagawa Station, JR East will verify the solar cells' power generation performance, installability, and adaptability to the installation environment. Once operations begin, it will be able to compare actual output against the estimated figure of about 5,800 kWh per year, and by measuring the power consumption of the lighting and other equipment, it can also evaluate how much of the required electricity solar power can cover. The announcement gave details such as the installation area and generating capacity, but the specific method for fixing the cells to the roof and the construction time slots have not been disclosed.

JR East intends to consider adoption at other railway facilities based on what it learns at Shinagawa Station and on future technology developments. Because roof shapes and the time available for construction differ from facility to facility, not only power generation results but also the conditions under which installation was possible will be important factors in choosing future sites.