On November 25, 2026, the Space Bureau of the U.S. Federal Communications Commission (FCC) conditionally authorized SpaceX to deploy and operate up to 1 million satellites for Starmind, its orbital data center plan. The concept is to put computing equipment on satellites and process data in low Earth orbit. According to the FCC, this is the first time a satellite constellation for this purpose has been authorized in the United States.

SpaceX must have its first satellite operating in the designated orbit by November 25, 2033, and complete deployment of the constellation by 2040. However, depending on the altitude of the orbits it uses and how satellites are disposed of at the end of their missions, additional authorization procedures may be required. The authorization covers satellite deployment and communications operations. It is a separate matter from whether a data center can be run stably in space from a technical standpoint.

AD

From 1 to 1 million satellites: the FCC's four-stage deployment deadlines

In its decision, DA 26-1273, the FCC Space Bureau waived the standard deployment milestone rules and set four milestones specific to Starmind. By each deadline, SpaceX must launch the required number of satellites, place them in the designated orbits, and operate them in accordance with the authorization conditions. Condition 10 of the decision states that the authorization will lapse if these requirements are not met by the deadlines.

Deadline Satellites that must be operating in designated orbits Requirement
November 25, 2033 At least 1 First satellite in operation
November 25, 2035 At least 100,000 10% of the authorized total in operation
November 25, 2038 At least 500,000 50% of the authorized total in operation
November 25, 2040 1,000,000 Deployment of the authorized constellation complete

If only the minimum of 500,000 satellites were operating at the 2038 deadline, SpaceX would have to put the remaining 500,000 into the designated orbits and bring them into operation in just two years, by 2040. The scale of launches required afterward depends on how deployment has progressed through 2038, but the latter half of the plan calls for deployment on a very large scale. The decision does not specify when commercial service will begin.

The decision took effect upon its release. The 15-year authorization term begins at 3:00 a.m. U.S. Eastern Standard Time on the day SpaceX certifies to the FCC that it has placed its first satellite in the designated orbit and is operating it in accordance with the authorization conditions. Condition 11 requires SpaceX to file this certification within five business days of beginning operation of the first satellite.

The main means of communication envisioned for Starmind is optical inter-satellite links using laser light. The plan is for Starmind satellites to connect not only with one another but also with first- and second-generation Starlink satellites. The radio communications the FCC has now authorized, by contrast, are Ka-band links used for satellite health monitoring, tracking, and command transmission, and are limited to backup and emergency use. The frequency bands are 18.8–19.3 GHz for satellite-to-ground communications and 28.6–29.1 GHz for ground-to-satellite communications.

Condition 1 requires that SpaceX not cause interference to other operators in these bands and that it not claim protection from interference by other operators. If SpaceX receives a written report of harmful radio interference, it must immediately stop the communications operations causing it and may not resume until the interference is resolved. It is also obliged to notify the FCC of the matter in writing.

Different debris-mitigation requirements on either side of 600 km

Of the six orbital altitude bands listed in the decision for normal operations, two are below 600 km and four are above. In paragraph 11 of the decision, the FCC Space Bureau found that SpaceX's orbital debris mitigation plan for satellites operating below 600 km complies with the rules. For satellites operating above 600 km, however, SpaceX must submit a final debris mitigation plan that meets all requirements before deployment and apply for a modification of the authorization.

Additional procedures are also required if satellites are to be disposed of without being deorbited into the atmosphere at the end of their missions. FCC rules require satellites that are below 2,000 km at end of mission to be reentered into the atmosphere as soon as possible and no later than five years afterward. SpaceX had requested a waiver of this rule so that satellites operating in orbits above 600 km could also be moved to Earth-orbiting disposal orbits or heliocentric orbits.

The FCC Space Bureau deferred its decision on the waiver, saying it lacked sufficient information to determine whether the proposed disposal methods comply with the rules. Condition 4 requires SpaceX, for satellites to be disposed of by any means other than atmospheric reentry, to apply for a modification of the authorization before deployment and operation and to justify its request for a waiver of the rules.

SpaceX has said it plans to first confirm that satellites function properly in lower orbits and then move them to higher orbits. Even if the initial insertion orbit is low, if the final operating altitude exceeds 600 km, SpaceX must submit a final debris mitigation plan and apply for a modification of the authorization before deployment. The decision does not fix the number of satellites to be deployed in each altitude band or how satellites will be disposed of.

Semiannual reports on deployment status and collision-avoidance record

Under Condition 6, SpaceX must report to the FCC on the operational status of its satellites every six months. Reports are due on January 1 and July 1 each year, covering periods ending November 30 of the previous year and May 31 of the same year, respectively.

The reports must state the number of close approaches to other space objects and, of those, the number that required collision-avoidance maneuvers or coordination with other satellite operators. They must also report the number of satellites removed from operation, excluded from further deployment, or reentered into the atmosphere. According to footnote 10 of the decision, once new FCC rules on satellite reporting that have been adopted take effect, the relevant provisions of those rules will apply to these three items.

The reports must further include the total number of satellites deployed as of the last day of the reporting period, orbital data for all of them, and the number of satellites that communicated with earth stations in the authorized Ka bands. These data make it possible to gauge the constellation's deployment status, but whether each milestone has been met is determined based on the number of satellites operating in the designated orbits in accordance with the authorization conditions as of the deadline. The decision does not say when, or to what extent, the individual reports will be made public.

AD

Technical challenges for orbital data centers: heat dissipation and sustained computing performance

Even with satellite deployment approved, how much computing can be sustained in space will need to be verified with real hardware. The FCC Space Bureau judged that comments submitted during the review on heat dissipation and technical feasibility fell outside the scope of its review of radio operations.

According to NASA technical materials for small satellites, heat generated by equipment inside a satellite is conducted mainly through the structural members of the spacecraft to radiating surfaces, from which it is released into space as thermal radiation. In terrestrial data centers, air or liquid coolant can carry heat away, but outside a satellite facing the vacuum of space, cooling by airflow is not available.

The amount of heat that can be released into space depends on the area and temperature of the radiating surface and on its emissivity, a measure of its ability to emit heat as infrared radiation. The orientation of the radiating surface and the heat received from the Sun and Earth also affect the satellite's overall heat balance. As a result, even with the same heat output from onboard computing equipment, the computational load that can be sustained over a long period will vary with sunlight conditions in orbit and the design of the heat-dissipation hardware.

Astrophysicist and author Adam Becker told the AP that cooling by thermal radiation is subject to physical limits, and that spreading the necessary equipment across many small satellites would be difficult in terms of both cost and technology.

Evaluating the performance of an orbital data center would require specifying the number of satellites used and the sunlight conditions in orbit, and then measuring how long a given computational load can be sustained. Component temperatures, power consumption, and actual computational throughput during that time would be recorded and checked against the heat dissipation achieved and the design conditions of the radiators. Running similar tests on different satellites and under different sunlight conditions would also make it possible to assess the reproducibility of computing performance. For a computing service used from the ground, the effective transfer speed via optical inter-satellite links and terrestrial lines, and the communication latency before results are received, would also be important metrics.

Neither the FCC decision, the NASA technical materials, nor the AP report presents results of performance tests on actual Starmind hardware. What SpaceX will certify to the FCC when it begins operating its first satellite is that it is operating in the designated orbit in accordance with the authorization conditions. In judging the practicality of Starmind as an orbital data center, what matters is how much computational throughput can be sustained, and for how long, while keeping the computing equipment within its allowable temperature range.