On November 18, 2026, the Global Electronics Association warned that surging AI demand is tightening the supply of printed circuit boards (PCBs) and related materials, and could affect production of automobiles, medical devices, defense equipment, and other products. Investment in PCB factories is advancing around the world, but procuring the glass cloth, resin, copper foil, and other materials needed for production is becoming a bottleneck for output increases. In its industry report, the association forecasts that supply constraints are likely to ease meaningfully only after mid-2028. Comparing the sharp rise in North American PCB orders with the materials expansion plans announced by Japanese companies shows that it takes time for added manufacturing capacity to translate into actual supply.
A printed circuit board is the foundation on which electronic components are mounted and connected to one another through wiring. Increasing output requires not only board-processing equipment but also securing the materials that form the wiring and insulating layers. For high-performance boards used in AI servers, demand for both manufacturing equipment and materials is expanding rapidly.
More layers in AI server boards are accelerating material shortages
A typical PC board has about 12 layers, while AI server boards are moving to 40 to 60 layers or more. In its warning issued on November 18, the Global Electronics Association cites this structural difference as a factor worsening material shortages. The more wiring and insulating layers a board has, the more glass cloth (a woven glass-fiber fabric that reinforces the board), resin, copper foil, and laminate materials it uses. In other words, even for the same number of boards, AI server applications require more material.
According to the association, lead times for high-layer-count boards have stretched to 16 to 20 weeks or more. In addition, large cloud providers are securing limited supply capacity in advance, leaving customers in automotive, industrial equipment, medical, defense, and other sectors pushed back in the queue. Rising demand for AI server boards is affecting procurement not only for AI-related companies but across a wide range of industries that use electronics. The association assessed that the risk facing the supply chain could be comparable in scale to the 2021 semiconductor shortage.
Board manufacturing capacity itself is being expanded. In Asia, which produces more than 90% of the world's PCBs, investment in new factories continues, centered on China and Southeast Asia. However, new plants need the same glass cloth, resin, copper foil, and other materials as existing ones, so if material supply cannot keep pace, the equipment cannot be fully utilized. The association's view is that increasing board manufacturing capacity alone will not resolve the shortage.
The association forecasts that board shortages will continue at least through the first half of 2027, and that a full supply recovery is unlikely before mid-2028. This outlook takes into account not only factory expansion plans but also upstream material supply capacity and increasingly complex manufacturing processes.
In North America, orders rose 56.1% while shipments grew only 13.3%
The state of supply constraints is also visible in the trends in board makers' orders and shipments. According to September statistics released by the Global Electronics Association on October 26, in the North American PCB market from January to September 2026, orders rose 56.1% year over year while shipments grew only 13.3%. In addition, according to August statistics released on September 30, the three-month book-to-bill ratio was 1.29, and it rose to 1.77 in September.
| Indicator / period | Orders | Shipments | Book-to-bill ratio |
|---|---|---|---|
| Jan–Sep 2026 cumulative, year over year | Up 56.1% | Up 13.3% | — |
| August 2026 alone, year over year | Down 35.0% | Up 23.5% | — |
| September 2026 alone, year over year | Up 229.4% | Down 6.4% | — |
| Three months through end of August 2026 | — | — | 1.29 |
| Three months through end of September 2026 | — | — | 1.77 |
Based on a representative sample of rigid PCB and flexible circuit manufacturers selling in the United States and Canada. The book-to-bill ratio is the value of orders over the past three months divided by sales over the same period, and does not indicate the quantity of shortages worldwide.
When the book-to-bill ratio exceeds 1, the value of orders received over those three months exceeds sales. However, monthly orders fluctuate considerably: they fell 35.0% year over year in August, then reversed sharply to rise 229.4% in September. Although cumulative orders from January to September are growing far faster than shipments, the single-month surge in September cannot be taken as evidence of sustained demand growth. The association also notes that orders are more volatile than shipments and are affected by seasonality and short-term factors, and urges readers to confirm trends that persist beyond three months.
Shawn DuBravac, the association's chief economist, explained that in addition to investment in data centers and networking, the aerospace and defense sectors are also pushing up board demand. At the same time, high-performance copper foil, resin, and electronic-grade glass cloth are supply constraints, affecting material prices and lead times. The rise in North American orders is consistent with the global material shortage warning, but order value and the quantity of materials actually available are different measures. Whether boards can be produced and shipped to match rising orders depends on how well materials are secured.
Panasonic and Mitsui Kinzoku expand output, with supply growth continuing beyond 2028
Japanese companies are also increasing production of AI-related board materials. On October 30, 2026, Panasonic Industry and Mitsui Kinzoku each announced plans to expand production capacity. Panasonic's MEGTRON is a high-performance multilayer board material that suppresses transmission loss of high-speed signals. Mitsui Kinzoku's MicroThin is an ultra-thin copper foil with a carrier, a thin copper foil attached to a supporting carrier, used in semiconductor package substrates and other applications requiring fine wiring. According to Mitsui Kinzoku, demand is growing not only for semiconductor package substrates for data centers and memory, but also for optical modules as optical-electrical convergence technology advances.
According to Panasonic's announcement, the company will increase MEGTRON production capacity at its Suzhou plant in China and its Ayutthaya plant in Thailand. In Suzhou, mass production will begin in December 2026 at Phase I equipment in a new building, and Phase II equipment, funded by additional investment, will come online in August 2028. In Ayutthaya, Phase I equipment will start operating in November 2027, followed by Phase II equipment in April 2029.
Mitsui Kinzoku's announcement set out a policy of raising MicroThin production capacity in stages from the second half of fiscal 2026 through fiscal 2028. The plan is to bring the combined capacity of the Ageo site and the Malaysia plant to 5.2 million square meters per month in the second half of fiscal 2026, 5.6 million in fiscal 2027, and 6.2 million in fiscal 2028.
| Company / material | Site / phase | Planned start / expansion | Investment / planned capacity |
|---|---|---|---|
| Panasonic, MEGTRON | Suzhou Phase I | Mass production starts December 2026 | Existing plan |
| Mitsui Kinzoku, MicroThin | Ageo and Malaysia combined | Second half of fiscal 2026 | 5.2 million sq. m per month |
| Panasonic, MEGTRON | Ayutthaya Phase I | Operations start November 2027 | Existing plan |
| Mitsui Kinzoku, MicroThin | Ageo and Malaysia combined | During fiscal 2027 | 5.6 million sq. m per month |
| Panasonic, MEGTRON | Suzhou Phase II | Operations start August 2028 | About ¥30 billion |
| Mitsui Kinzoku, MicroThin | Ageo and Malaysia combined | During fiscal 2028 | 6.2 million sq. m per month |
| Panasonic, MEGTRON | Ayutthaya Phase II | Operations start April 2029 | About ¥37 billion |
Based on plans announced by both companies on October 30, 2026. Calendar months and fiscal years follow each company's usage. All are planned figures, and production capacity differs from actual shipment volume.
Panasonic's announced total investment in AI-related businesses is about ¥92 billion, of which about ¥67 billion will go to increasing production of the MEGTRON board material. Of the remaining roughly ¥25 billion, about ¥17 billion is planned for increasing production of SP-Cap conductive polymer aluminum electrolytic capacitors, and about ¥8 billion for building a research and development facility for next-generation semiconductor materials. For the MEGTRON expansion, Phase I equipment at Suzhou and Ayutthaya will come online in 2026 and 2027, while the Phase II equipment announced this time will begin operating in 2028 and 2029. Suzhou is positioned as a base serving the Chinese circuit board market, and Ayutthaya as one serving the Southeast Asian market.
Mitsui Kinzoku moved up its earlier plan of 6 million square meters per month by fiscal 2028, raising capacity for that year to 6.2 million square meters. This will be achieved through productivity improvements at the Ageo site and by bringing forward the introduction of some equipment, with no additional capital investment required for the plan change. The company is working to expand supply capacity not only by building new plants but also by improving existing facilities.
Upward pressure on material prices is also building. In a price revision announced on June 26, Panasonic said it would raise prices of MEGTRON/XPEDION copper-clad laminates by 10% and prepreg by 15% for shipments from August 1. Prepreg is a reinforcing material impregnated with resin, used in the board lamination process. The company cited the impact of the situation in the Middle East on petrochemical supply and international logistics, as well as soaring raw material prices for resin, solvents, and other inputs, as reasons for the increase.
Both companies' expansion plans respond to growing demand for AI-related board materials, but they do not directly indicate when the worldwide supply shortage will be resolved. MEGTRON and MicroThin are both materials for specific applications, and supply capacity for other materials such as glass cloth and resin will not increase at the same time. It is also necessary to distinguish between when equipment begins operating and when all the necessary materials are available to actually produce boards.
Avoiding over-ordering and securing alternative materials are key challenges
As measures against the shortage, the Global Electronics Association recommends that manufacturers share realistic demand forecasts, avoid duplicate orders, and qualify alternative sources for laminate materials, prepreg, and copper foil. When lead times lengthen, customers tend to place the same demand with multiple companies to secure supply. However, if the total volume of orders manufacturers receive then exceeds actual demand, it can lead to a mistaken demand outlook when deciding whether to expand supply capacity. If orders are later canceled, expanded equipment could end up in excess.
The association also calls on governments to treat boards and related materials as a strategic supply chain on a par with semiconductors, supporting investment incentives for manufacturing equipment, faster permitting, and research and development of alternative materials. Because introducing new materials requires performance evaluation and approval by customers, it also proposed support for those processes. It further says that loan guarantees and subsidies will be needed to maintain critical manufacturing capacity in case advance orders are canceled and demand is revised in 2027. This is a recommendation anticipating a possible fall in demand, not a forecast that the supply shortage will end in 2027.
In the near term, concrete checkpoints will be the start of mass production at Panasonic's Suzhou Phase I in December 2026 and the capacity increase for Mitsui Kinzoku's MicroThin in the second half of fiscal 2026. What matters is not only that the equipment starts operating, but also whether the materials produced pass customer evaluation and approval and ship in the planned quantities. If supply expansion and customer adoption proceed as planned, newly built and expanded board factories will have more options for procuring the materials they need.