On November 19, 2026, the US Senate passed the bipartisan "Bipartisan American Affordability and Jobs Act of 2026 (BAAJA)" by a vote of 62 to 33. The bill would speed up permitting for power plants, transmission lines, and other energy infrastructure. It also includes a provision requiring data centers to bear the cost of grid upgrades. In an amendment released on November 7, the previous 20 MW minimum facility size was removed. The bill has now gone to the House, but as of November 20 only 12 session days remain in the current House session. Whether a bill that could significantly change how data centers pay for power infrastructure becomes law depends on whether the House can bring it to a vote in that limited time.
20 MW Threshold Removed, Widening the Data Centers Subject to Cost Responsibility
According to materials released by the office of Senator Cynthia Lummis, BAAJA tightens deadlines for environmental review under the National Environmental Policy Act (NEPA) and, in principle, sets a 150-day limit for filing lawsuits seeking judicial review. Under the current system, permitting reviews for large energy projects can take five years or more, and the bill aims to encourage construction of power plants and transmission facilities by shortening the process. In the Senate vote, 14 Democrats and one independent joined most Republicans in voting yes. Republicans Josh Hawley and Mike Rounds voted against it.
The data center provisions are explained in detail in an analysis by the law firm White & Case. The bill establishes a national policy that owners and operators of computing facilities such as data centers should bear the full cost of new grid infrastructure upgrades they require, as well as the cost of transmission service, including for existing facilities. It also bars shifting those costs onto other customers, such as households and businesses, through electricity rate-setting or cost allocation.
In the earlier version of the bill, the computing facilities subject to cost responsibility were limited to those of 20 MW or more. The amendment released on November 7 removed that threshold, so data centers of any size are covered. The main steps from introduction to Senate passage were as follows.
| Date | Event |
|---|---|
| Sept. 30 | BAAJA introduced in the Senate. The original version limited coverage to facilities of 20 MW or more |
| Nov. 7 | Amendment released, removing the facility size threshold |
| Nov. 9 | Senate clears a procedural vote (cloture) to move forward with debate |
| Nov. 18 | Senate adopts the amendment 69-27 |
| Nov. 19 | Senate passes the bill 62-33 and sends it to the House |
Facilities under 20 MW that were previously exempt could now be required to bear these costs under the amended provision. With wider coverage, the assumptions data center operators use to estimate power equipment construction costs and transmission charges would also change. However, the specific rate structures and how costs are allocated will depend on guidance the Federal Energy Regulatory Commission (FERC) issues after the bill becomes law.
Broader Than Existing FERC Measures, Extending Cost Responsibility to Existing Facilities
What distinguishes BAAJA is that it asks not only new data centers but also existing transmission customers to revisit how costs are borne. According to White & Case, the bill directs FERC to issue a policy statement on cost responsibility within 90 days of enactment. It would also require a review of the transmission service pricing policy established in 1994, including revisions to rates applied to existing transmission customers.
FERC is already pursuing measures to address large power demand. Its existing show cause order covered demand exceeding 50 MW at a single site connecting to the grid at voltages above 69 kV, within the jurisdictions of six regional transmission organizations. BAAJA, by contrast, sets no minimum facility size and also covers existing transmission customers. White & Case points out that the bill calls for broader cost responsibility than FERC's existing measures.
Changes to transmission buildout and cost responsibility could also affect how data centers procure power. An analysis published by Rhodium Group on November 2 found that if BAAJA led to more transmission construction and data centers could draw power from the grid rather than from dedicated gas-fired generation, associated greenhouse gas emissions could be 31–90% lower. That figure comes from comparing scenarios with different power mix and other conditions, and it is based on the original version of the bill introduced on September 30. It does not represent the emissions reduction from the cost responsibility provision itself.
The bill also includes mechanisms to support local governments that host data centers. The US Department of Energy (DOE) would independently analyze how planned data centers affect local power grids, water resources, infrastructure, and retail electricity rates, and provide the results to state, local, and tribal governments. It would also prepare standard materials summarizing what local governments should ask utilities and data center operators.
The direct impact on Japan would be limited, but it could indirectly affect AI services delivered through US data centers. If the power infrastructure costs borne by US operators rise, that could bear on the operating costs of AI services and on future capital investment plans.
12 House Session Days Left, and Political Divisions That Could Block Passage
BAAJA passed the Senate with 62 votes and bipartisan support. President Trump also supports the bill and has indicated he will sign it if it clears the House. Senator Shelley Moore Capito, a co-sponsor, has urged House leadership to pass it quickly. The House passed a narrower, more industry-friendly permitting reform bill in 2025, so support for reform itself exists.
However, two obstacles remain in the House: the calendar and political divisions. According to White & Case, as of November 20 there were 12 House session days left in the second session of the 119th Congress, and some members who lost in the November midterm elections may not return to Washington after the Thanksgiving recess. The Speaker is considering either a vote under "suspension of the rules," which requires a two-thirds majority, or a path through the Rules Committee review and passage by an ordinary majority.
Opposition to the bill is also strong. In the Senate, Alex Padilla voted against it, and Maria Cantwell criticized the deliberations as rushed. Environmental groups including the Sierra Club and the National Wildlife Federation also oppose it, arguing that limits on judicial review and changes to NEPA and other laws weaken environmental protections. Reuters likewise cites concerns over environmental protection and tribal rights as a major factor that could block the bill.
House Democratic Leader Hakeem Jeffries has also said the bill falls short on environmental protection. Investment firm TD Cowen lowered its estimate of the bill's chance of passage from about 40% before the midterms to 25% after the election. That assessment predates the Senate vote on November 19, however, and it is unclear whether the outlook has since been updated.
The Senate vote has raised expectations for the bill, but whether the House will reach a vote during the remainder of the session remains uncertain. If it does become law this session, the first concrete milestone would be FERC's policy statement, due within 90 days of enactment, which will show how data center cost responsibility is put into practice.
Even if the bill fails, the debate over data centers will not end. According to Reuters, when the new Congress convenes in January 2027, Democrats, who will hold the majority, are expected to introduce a series of bills targeting AI and data centers. For now, the key question is whether BAAJA, which won a bipartisan 62 votes in the Senate, will get a House vote in the 12 session days that remain.