Building the permanent lunar base NASA is pursuing requires technologies in seven areas: power supply, in-situ resource utilization, life support, dust mitigation, radiation shielding, construction robotics, and communications and navigation. But how far each of these can actually be used on the Moon varies widely.
In March 2025, an electrodynamic dust shield and a satellite-positioning receiver operated properly on the lunar surface, delivering results. Meanwhile, a drilling experiment and a cellular network demonstration conducted around the same time achieved only part of their objectives. For the fission reactor expected to anchor power supply, NASA has set a goal of landing it on the Moon in 2030, but as of August 2026 only a draft procurement document had been released. Below, we sort out the demonstration status and future plans of each technology using NASA and other public materials.
How Far Have the 7 Technologies Needed for a Moon Base Come?
For each area, we summarize the most advanced demonstration environment confirmed so far and the main upcoming plans.
| Technology area | Demonstration stage | Main results | Upcoming plans |
|---|---|---|---|
| Power supply | Ground testing / development plans | Prototype vertical solar array thermal-vacuum tested in summer 2024. Draft procurement for fission reactor LR-1 released in August 2026 | LR-1 targeted to land on the Moon in 2030. Solicitation for integrated power system planned for early 2027 |
| In-situ resource utilization | Ground testing; partial lunar demonstration | CaRD extracted 0.195 g of oxygen from simulated regolith (August 2025). PRIME-1 operated its instruments on the Moon but did not reach drilling | PROMISE will survey ice down to about 1 m underground. Launch planned for late 2028 |
| Life support | Low Earth orbit | Demonstrated 98% total water recovery on the ISS (2023). NASA's reference page describes it as about 90% | No lunar demonstration schedule given |
| Dust mitigation | Lunar demonstration | Electrodynamic dust shield (EDS) operated on Blue Ghost Mission 1 (March 2025) | No schedule given for the next lunar demonstration |
| Radiation shielding | Research stage | Shielding structures being considered in ARMADAS construction robot research | PROMISE to measure the radiation environment, with launch planned for late 2028 |
| Construction robotics | Ground testing | Excavation robot IPEx operated in a simulated lunar environment | No schedule given for deployment to the Moon |
| Communications and navigation | Lunar demonstration | GNSS receiver LuGRE succeeded in lunar positioning. Nokia's 4G/LTE network ran for 25 minutes (March 2025) | 5G lunar demonstration planned by the end of 2028. Communications satellite deployment demonstration also planned for 2028 |
Note: Based on public materials as of November 16, 2026. "No schedule given" means that the NASA materials and announcements consulted do not state a specific date.
Results from the lunar surface are concentrated in two missions that landed in March 2025: Firefly Aerospace's Blue Ghost Mission 1 and Intuitive Machines' IM-2. Meanwhile, power supply, resource utilization, and construction robotics, which are essential for continuous base operation, remain mainly at the ground-testing stage.
In construction, NASA's excavation robot IPEx uses counter-rotating bucket drums to dig and haul lunar soil. NASA's design goal is to excavate up to 10,000 kg of regolith in about 15 Earth days, equivalent to a lunar daytime. At a test site at Kennedy Space Center, it confirmed operation under varied lighting conditions and with obstacles such as rocks, but NASA has not said when it will be sent to the Moon.
Can a Fission Reactor Powering a Moon Base Land by 2030?
On January 13, 2026, NASA and the U.S. Department of Energy announced a memorandum of understanding to complete development, fueling, licensing, and launch preparation for a lunar fission reactor by 2030. NASA's lunar technology plan targets landing the first lunar fission reactor, Lunar Reactor-1 (LR-1), in 2030.
Specific development requirements appeared in a draft procurement document released on August 30, 2026. According to New Space Economy, which analyzed NASA's procurement documents, LR-1 is required to meet the following conditions:
- Electrical output of 20 kWe or more
- Five years of continuous operation without maintenance
- Operation at 84 to 90 degrees south latitude
- Ability to run through darkness of 354 hours or more
- Mass under 15 metric tons
354 hours is about 14.75 days, close to the roughly 15-day length of the lunar night as described by NASA. This requirement is meant to keep power flowing through long periods of darkness when solar cells cannot generate electricity. The five-year maintenance-free requirement assumes long-term operation without sending maintenance crews from Earth. The operating range of 84 to 90 degrees south latitude corresponds to the Moon's south polar region, where the Moon Base plan envisions building the base.
The draft procurement sets the first development phase (Phase 1) at 18 months or less and calls for a flight design needed for the preliminary design review (PDR), integrated testing with an engineering test unit (ETU) that simulates the reactor's heat with electric heaters, and radiation testing of components. Building the actual flight reactor with nuclear fuel comes in a later phase. NASA has indicated it will issue task orders to multiple companies in Phase 1, but it reserves the right not to make any selections.
The schedule leaves little margin. Phase 1 alone can take up to 18 months, so detailed design, flight reactor fabrication, and launch authorization would all need to be completed by 2030. In a feature in Aerospace America, Steve Sinacore, program lead for the SR-1 nuclear electric propulsion spacecraft, expressed the view that regulatory reform and technological maturation have raised the odds of success. LR-1 is planned to be developed under industry leadership, but New Space Economy points to the tight development window that remains.
In parallel with the reactor, development of solar-based power systems is also progressing. The vertical solar array NASA is considering deploys solar cells on masts up to 20 m tall, and in summer 2024 Honeybee Robotics and Astrobotic tested a prototype in a thermal-vacuum chamber at Johnson Space Center.
On November 7, 2026, NASA also announced it had ordered components for "miniCAST," a power and communications tower combining solar cells, batteries, and wireless power transmission. Honeybee Robotics is responsible for energy storage, Redwire for power generation, and Yank Technologies for the wireless power transmission equipment. The order covers components only; NASA will carry out system assembly and testing. A separate solicitation for the integrated power system is planned for early 2027.
How Far Has Technology for Using Lunar Water and Oxygen Come?
A permanent lunar base will need to secure and reuse water and oxygen on-site wherever possible rather than keep shipping them from Earth. In life support, the foundation for this, high water recovery rates have already been demonstrated on the International Space Station (ISS).
A NASA reference page updated on April 4, 2025, describes the ISS water recovery rate as about 90%. A 2023 announcement, meanwhile, reported demonstrating that adding a Brine Processor Assembly (BPA) to the Environmental Control and Life Support System (ECLSS) can achieve 98% total water recovery. Brine is the concentrated liquid left after urine distillation, and the BPA is a device that recovers the remaining water from it. According to Jill Williamson, who works on the ECLSS water system, total water recovery before the BPA was 93 to 94%.
A 98% total recovery rate corresponds to losing only 2 pounds when 100 pounds of water is processed. However, NASA's 2023 announcement said that 98% was demonstrated, not that this level is always maintained in routine operation. Nor does the reference page make clear which state, before or after the demonstration, its roughly 90% figure refers to.
Research on extracting oxygen from lunar resources is also advancing. According to a June 2026 conference paper posted on NASA's Technical Reports Server (NTRS), the integrated prototype of the Carbothermal Reduction Demonstration (CaRD) extracted oxygen from simulated regolith in the form of carbon monoxide (CO) in a test conducted in Houston on August 28, 2025. NASA's lunar technology page gives 2026 for the integrated prototype test, a different year from the actual test date in the conference paper.
The test was conducted at Johnson Space Center, where concentrated sunlight heated simulated regolith and the resulting gas was analyzed. For gas measurement, it used an analyzer developed by Kennedy Space Center based on the MSOLO mass spectrometer, and the reaction was confirmed by detecting carbon monoxide. The reactor is built by Sierra Space.
In the August 28 test, using 0.38 kWh of solar energy reaching the concentrator mirror, 0.195 g of oxygen was extracted. This corresponds to about 0.51 g per kWh of energy incident on the mirror. According to the conference paper, this value exceeds the performance target that was set. However, it is not known how much oxygen can be extracted from actual lunar regolith by the same method, and a lunar demonstration is needed.
In resource surveying, Intuitive Machines' IM-2, which landed on March 6, 2025, could not carry out its experiments as planned. The lander tipped onto its side, and its batteries ran out before the drilling equipment and other instruments could be fully operated. TRIDENT, the drill aboard NASA's PRIME-1 instrument suite, confirmed its range of motion in the space environment, and the MSOLO mass spectrometer detected gas thought to originate from the lander's propulsion system, but the original goal of drilling into the lunar ground to examine subsurface resources was not achieved.
As the next resource exploration plan, NASA is developing the nuclear-powered rover PROMISE. PROMISE will use TRIDENT to dig up regolith in 10 cm increments down to about 1 m underground to check for ice. Volatiles released from the excavated material will be analyzed with MSOLO. Launch is scheduled for late 2028, and the plan is to take another run at the subsurface resource analysis that could not be carried out on IM-2.
Dust Removal and Satellite Positioning Proven on the Moon; Communications Network Faces Challenges
In the March 2025 lunar missions, important results were obtained in dust removal and satellite positioning.
Firefly Aerospace's Blue Ghost Mission 1 landed on the Moon on March 2, 2025, and demonstrated NASA's electrodynamic dust shield (EDS). The EDS uses an electric field to remove regolith adhering to surfaces, and it succeeded in removing dust from glass and thermal-radiator material samples exposed on the lunar surface. Its operation was confirmed on the actual lunar surface rather than in a ground-based simulated environment.
The same lander also carried LuGRE, a Global Navigation Satellite System (GNSS) receiver jointly developed by NASA and the Italian Space Agency (ASI). At 06:51:35 UTC on March 3, 2025, LuGRE used GPS and Galileo signals to compute the first GNSS positioning solution on the Moon. The lander's mission ended on March 16. A paper summarizing the results describes it as, to the authors' knowledge, the first demonstration of acquiring, tracking, and navigating with GNSS signals near the Moon and on its surface.
GPS and Galileo are satellite positioning systems originally designed for use on Earth. The LuGRE experiment confirmed that their signals can be used for positioning on the Moon as well. However, signal reception conditions differ greatly from those on Earth. According to the paper, the carrier-to-noise-density ratio (C/N0) of the GPS L1 signal received in flight was roughly 7 to 12 dB below pre-flight simulations across all the data. The research team says that using GNSS near the Moon requires high-gain antennas, and that because the signals arriving from Earth are strongly skewed in direction, combining GNSS with other navigation methods is a promising approach.
Meanwhile, the demonstration of a cellular network on the Moon achieved only partial success. The lunar 4G/LTE network "LSCS," developed by Nokia Bell Labs and carried on Intuitive Machines' Athena lander, powered up the network during the 25 minutes it could be supplied with power and transmitted operational data to Earth. However, the planned first cellular call on the Moon could not be made.
According to Nokia, power supply was severely constrained by the orientation of Athena's solar panels after landing. In addition, the terminal module aboard the Micro Nova Hopper could not connect to the network because of power shortages and the harsh environment inside the crater, which pushed temperatures well below the operating range. NASA also describes the experiment as having partially achieved its original objectives.
The next communications technology under development is 5G. On September 30, 2026, NASA awarded Modulate Space a fixed-price contract of about $38 million (about 6 billion yen) through Glenn Research Center. It covers development of a lunar 5G network incorporating Wi-Fi 6, with a ground demonstration period of October 1, 2026 to January 31, 2028 and a lunar flight demonstration period of November 30, 2026 to December 31, 2028. The lander that will carry it to the Moon has not been announced. On November 7, NASA also announced plans for a 2028 demonstration using SpaceX's Starship to deploy communications satellites in the space between Earth and the Moon.
Yen conversion is based on 158.88 yen to the dollar, published by the Bank of Japan on November 11, 2026.
Radiation Protection Starts With Measuring the Environment; Shielding Structures Remain in Research
Because the Moon lacks a thick atmosphere or a global magnetic field like Earth's, measures are needed to protect astronauts on long stays from cosmic radiation. However, technologies for measuring the radiation environment and the development of shielding structures that actually protect crews are at different stages.
PROMISE, developed by NASA's Jet Propulsion Laboratory (JPL), is built from spare parts for Mars rovers and is designed to survive the lunar night using a radioisotope power source (MMRTG). In addition to its subsurface resource survey instruments, it will carry the radiation detector RAD and plans to measure the lunar surface radiation environment during an 18-month primary mission. It is slated to be delivered by Blue Origin's Mark 1 lander.
As for shielding structures to protect crews, NASA's construction robotics research "ARMADAS" lists radiation shielding as one use for structures assembled by robots. However, what PROMISE will do is measure the radiation environment, not verify shielding performance. The materials NASA has published on both projects give no specific schedule for demonstrating shielding structures on the Moon.
Moon Base Lander Missions Pushed to 2027 or Later
While technology development for building the lunar base advances, the schedule for the landing missions that carry demonstration equipment to the Moon has also changed.
In May 2026, NASA had targeted launching all three landing missions, Moon Base I to III, in 2026. By November, however, the schedules for all three had been changed to 2027 or later. The new schedules were reported by trade publications based on what NASA officials said in talks and briefings, and they do not appear in NASA's official November 7 announcement.
The main schedule changes related to the Moon Base plan are as follows:
| Date | Main announcement or change | Source |
|---|---|---|
| End of February 2026 | Artemis III objective changed from a lunar landing to a lander docking test in low Earth orbit | Aerospace America |
| March 24, 2026 | At Ignition, NASA explained it would pause the Gateway lunar-orbit outpost in its current form and redirect most resources to the Moon Base plan | NASASpaceflight.com |
| May 26, 2026 | Announced targets to launch Moon Base I as early as fall 2026, II later that year, and III within the year | NASA |
| September 2026 | Moon Base I's Mark 1 Endurance and III's Nova-C Trinity moved to the first half of 2027 | Aerospace America |
| October 2026 | Artemis III launch target set for summer 2027 (May to September), and lunar landing targets for Artemis IV and V set for 2028 | Aerospace America |
| November 7, 2026 | Moon Base II's Griffin explained to be no earlier than January 2027 | SpacePolicyOnline |
| November 7, 2026 | CLPS 1.0 contract ceiling raised from $2.6 billion to $4.2 billion; eight companies selected for CLPS 2 | NASA |
The reasons for the delays differ by mission. For Blue Origin's Blue Moon Mark 1 Endurance, used for Moon Base I, NASA and Blue Origin cite the May 2026 New Glenn launch pad explosion. For Astrobotic's Griffin, used for Moon Base II, Carlos García-Galán, who is in charge of the Moon Base plan, cited the lunar launch window and ongoing engine testing as delay factors. For Intuitive Machines' Nova-C Trinity, used for Moon Base III, the company's CEO said on an August earnings call that the launch would slip to the first quarter of 2027, but the Aerospace America article gives no specific reason.
Plans to increase the number of lunar landings per year have also been pushed back. According to SpacePolicyOnline, Lori Glaze, who leads NASA's Mission Directorate for human spaceflight, expects four Commercial Lunar Payload Services (CLPS) landings in 2027: the three delayed missions plus one by Firefly Aerospace. Nicky Fox, head of the Science Mission Directorate, explained that the goal of 10 landings per year now begins in 2028. At Ignition in March 2026, NASA had said it aimed for 10 landings per year from 2027 to 2029.
Meanwhile, NASA is expanding the contract capacity for lunar delivery itself. On November 7, 2026, it raised the CLPS 1.0 contract ceiling from $2.6 billion to $4.2 billion and selected eight companies for CLPS 2, which has a contract capacity of up to $10 billion over 10 years.
The main payloads the three delayed landing missions will carry do not necessarily match the technology demonstrations for the seven areas the base needs. According to NASA's May announcement, Moon Base I will carry a stereo camera and laser reflector to image the interaction between engine plumes and the lunar surface during landing, II will carry Astrolab's FLIP rover, and III will carry Lunar Vertex, which studies swirl patterns on the lunar surface.
Future lunar demonstrations directly related to the seven areas include PROMISE's subsurface resource and radiation environment survey, scheduled to launch in late 2028, and Modulate Space's 5G demonstration, planned for completion by the end of 2028. According to Aerospace America, NASA intends to advance the first phase of the Moon Base plan by 2029 and place the base's initial facilities by 2030. This also overlaps with the 2030 landing target for the LR-1 fission reactor.
The immediate concrete milestones are whether the LR-1 draft procurement advances to a final solicitation and how many contracts are awarded in Phase 1. A solicitation for the solar-based integrated power system is also planned for early 2027. With PROMISE's survey of subsurface ice planned for late 2028, there will be more opportunities to compare development plans against actual test results for two foundational technologies: base power supply and in-situ resource utilization.